Starting in December 2025, we’ll begin publishing regular monthly reports on the Time Square 10 construction project . These reports will feature real photos from the site, construction stages, and project progress, so you can see how your home/investment is growing, not just pretty renderings.
TIME SQUARE 10 REPORT 9.July.2026 / download:
TIME SQUARE 10 REPORT 19.June.2026 / download:
Time Square 10 Ocean View
Progress Construction / 09.06.2026
report: As of 09/june/2026, foundation work continues on the first coastline of Sihanoukville.
Current progress:
- 180 out of 197 drilling piles have been completed — 91% ready.
- 109 out of 197 Sonic Tests have been conducted — 55% ready.
- Work continues on drilling the remaining piles.
- Checks of reinforcement, depth of wells and quality of concrete works are carried out.
- Materials are being monitored and the construction site is being prepared.
TIME SQUARE 10 REPORT 9.June.2026 / download:
TIME SQUARE 10 REPORT 29.April.2026 / download:
What has been done to date (report as of December 9, 2025):
- A Ground Breaking ceremony was held with the participation of the developer, contractor and investors.
- They brought the equipment to the site and prepared the construction site.
- The area is being prepared for piling work.
- Geodetic work and site marking have been carried out.
- The delivery and inspection of building materials (metal, structures, etc.) has begun.




See the detailed construction report for Time Square 10 as of January 2026:




Time Square 10 construction progress as of March 2026:







More about the project: