UC88 Wyndham Garden – Project Construction and Finishing Progress Reports

The format is 46 floors, 459 units, 5-star service standards, and premium finishes in line with Wyndham’s international standards. The project combines residences with the full hotel service of the Wyndham brand, which operates a network of over 9,280 hotels in 95 countries.

The developer is UC Group , a 30-year-old company that has completed The View, Golden One, and other landmark projects. The contract with Wyndham is official, guaranteeing a consistent level of service and management.

More about the project:

Construction & finishing report/project: UC88 Tower – june 2026

The project is steadily approaching completion. The construction works are in the final stage, and the final appearance of the complex is already clearly visible. Let me remind you that this is one of the few projects in Cambodia that offers guaranteed rental income, which makes it especially interesting for investors who are focused on receiving passive income immediately after the transfer of the facility.

Construction & finishing report/project: UC88 Tower – december 2025

Status: January 2026

  • The building is fully erected, the facade and glazing are completed.
  • Active finishing works are underway at all levels
  • Basement floors (B1–B3): marble finishing, elevator lobbies, technical and storage areas
  • Lower and middle floors: installation of engineering systems (MEP), partitions, ceilings, tiles, plastering
  • Upper floors: fine finishing, built-in furniture, sanitary ware
  • Lobby and public areas: furniture, lighting, decorative elements are almost complete
  • Roofing and rooftop areas: swimming pool, spa, gym, helicopter roof, technical work and final inspections